Description |
|
The IBR is a verification review process in which technical staff demonstrates that the entire Project baseline is in place, together with a realistic budget to accomplish all planned work to develop the Performance Measurement Baseline (PMB). It is conducted by PMs and their technical staffs or Integrated Product Teams (IPTs) on contracts requiring compliance with DoD Earned Value Management System (EVMS) criteria requirements within 6 months after contract award. |