Description |
|
This activity is the review for the first decision point of the Defense Acquisition Management Framework. It authorizes entry into the Concept Refinement (CR) phase. The principal document at this decision point is the Initial Capabilities Document (ICD) which also contains an approved plan for conducting an Analysis of Alternatives (AoA). |
CBM Stakeholder(s) (1) |
|
WSLM |
Activity Positioning |
|
Level Number | 1311 |
Leaf-Level? | |
Node-Tree Only? | |
External? | |
|
Parent Operational Activity (1) |
|
Conduct Acquisition Decision Review |
Child(ren) Operational Activity(ies) (0) |
|
|
Diagram(s) (1) |
|
|
BPM Process(es) (0) |
|
|
Business Capability(ies) (0) |
|
|
Business Rule(s) (0) |
|
|
Condition(s) (0) |
|
|
DFMIR/FFMIA(s) (0) |
|
|
FEA BRM(s) (3) |
|
Information Management Information Security Lifecycle/Change Management |
Measure(s) (0) |
|
|
Operational Node(s) (0) |
|
|
Project(s) (0) |
|
|