Budget At Completion - Program Manager
Type - Data Synonym
Description:
The Program Manager's sum of the original budgets plus or minus budget changes resulting from contract changes, internal replanning, and application of Management Reserve (MR).
Information Exchange:
Integrated Master Schedule